This company specializing in the manufacture of automotive glazing is located in the industrial zone of Kenitra, according to a statement by the Office, pointing out that the project was completed despite the difficult context of total mobilization for the fight against Covid-19.
The project consists of the construction of a 60/22KV substation on the site of the AGC plant with two 60 KV outgoing bays, one 60 KV busbar, two complete 60/22 KV transformer bays and two 60/22KV power transformers of 25MVA each.
It also aims to build two 60 KV underground lines of 3.7 km each, from the 60/22KV Atlantic Free Zone Investment substation, as well as two 60/22KV spans at the Atlantic Free Zone Investment substation.
The project is part of the actions carried out by ONEE to support the industrial sector through the development of electrical energy supply projects.
This is a new achievement that comes in a particular context of general mobilization for the fight against the Covid-19 pandemic and in response to the national duty to guarantee the country's supply of electricity and drinking water as well as the liquid sanitation service.